Hornsea 3 developers prepare to install first offshore wind turbine

Developers of the 2.9GW Hornsea 3 offshore wind farm are preparing to install the project’s first wind turbine. The facility is set to become the largest in the world upon completion. Luke Bridgman, managing director of Hornsea 3, confirmed that two wind turbine installation vessels, Wind Ally and Wind Orca, are currently at the ports of Hull and Able Seaton. They are getting ready to load the first turbine parts for installation on the foundations.

The project will utilise a total of 197 Siemens Gamesa SG 14-236 wind turbines, each rated at 14MW. Bridgman noted that the team is also working with array cables, with a couple already in place and further work scheduled to continue through the end of the year. Monopile installation is underway and will proceed alongside the completion of the export cable. Both export circuits are expected to be installed end to end before the year concludes.

By this time in 2027, Bridgman stated that both transmission circuits will be in and energised, along with all foundations and array cables. The final few turbines are scheduled to be installed by November of next year. Danish renewables company Ørsted is developing the offshore project and holds a 50 per cent ownership stake, alongside funds owned by Apollo Global Management.

Post Disclaimer

The following content has been published by Stockmark.IT. All information utilised in the creation of this communication has been gathered from publicly available sources that we consider reliable. Nevertheless, we cannot guarantee the accuracy or completeness of this communication.

This communication is intended solely for informational purposes and should not be construed as an offer, recommendation, solicitation, inducement, or invitation by or on behalf of the Company or any affiliates to engage in any investment activities. The opinions and views expressed by the authors are their own and do not necessarily reflect those of the Company, its affiliates, or any other third party.

The services and products mentioned in this communication may not be suitable for all recipients, by continuing to read this website and its content you agree to the terms of this disclaimer.

Our Socials

Recent Posts

Stockmark.1T logo with computer monitor icon from Stockmark.it
Loading Next Post...
Loading

Signing-in 3 seconds...

Signing-up 3 seconds...